    • Naugarh Gad Hydroelectric Project (8.5 MW)
    • Upper Naugarh Gad Small Hydroelectric Project (8MW)
    • Upper Chameliya Hydroelectric Project (40MW)
  • Solar Projects
    • Bardaghat 1 MW Solar PV Project
    • Chanauta 1.5 MW Solar PV Project
    • Kawasoti 1 MW Solar PV Project
    • Kawasoti 0.5 MW Solar PV Project
    • Dhalkebar 1 MW Solar PV Project
    • Parwanipur 8 MW Solar PV Project
    • Simara 1 MW Solar PV Project
    • Chandranigapur 4 MW Solar PV Project
  • News & Reports
  • Gallery
  • Career
  • Contact

UPPER CHAMELIYA HYDROELECTRIC PROJECT (40MW)

 

 

Upper Chameliya Hydroelectric Project is a run-off-river type project located Lattinath, Guljar and Tapoban VDC's of Darchula district, Mahakali zone, Far Western Region of Nepal. This Project Utilizes the 40% probablility discharge of 22.79 m3/s with gross head of 215m to generate 40 MegaWatt power. The generated power will be evacuated through 16 km long, 132kV double circuit transmission line from project switchyard to Balanch Substation. The Intake and Weir is proposed downstream of the confluence of Rugru Gad and Chameliya river at Guljar VDC. Major Structures of the Project are Diversion Weir & Intake, Settling Basin, Headrace Pipe, Surge Tank, Penstock Pipe, Powerhouse and Tailrace canal. The Powerhouse site is proposed at Lama Bagar of Lattinath VDC, Darchula district just u/s the confluence of Odkhet Khola and Chameliya river. The whole alignment runs along the left bank of the river.  

 

Project Description

 

Project Details
Project Name : Upper Chameliya Hydroelectric Project
Development Region : Far Western
Zone : Mahakali
District : Darchula
Intake Site : Guljar VDC
Powerhouse Site : Lattinath VDC
Geographical Co-ordinates
Latitude : 29°44'20" N to 29°46'57" N
Longitude : 80°46'50" E to 80°49'12" E
General
Name of River : Chameliya River
Nearest Town : Gokuleshwor
Type of Scheme : Run-of-river
Gross Head : 215 m
Net Head : 204.61 m
Installed Capacity : 40 MW
Hydrology
Catchment Area : 656.3 km2
Average Annual Precipitation : 2000 mm
Monsoon Wetness Index : 1500 mm
Design Discharge : 22.79 m3/s
Diversion Weir and Intake  
Type of Weir : Gravity Type Concrete Overflow Spilway
Length of Weir : 35 m
RL of the Weir Crest Elevation : 1265 m from the MSL
Intake Type : Side Intake
Size : 4.00 m x 2.50 m x 4 nos.
Desanding Basin
Type : Dofour Chamber
Trapped particle size : >0.2 mm
Length : 120 m
Headrace Pipe
Type : Mild Steel 
Shape : Circular
Length : 5 km
Diameter : 3.50 m
Surge Tank
Type : Simple Cylindrical Tank
Dimension : D = 18 m, H = 30 m
Penstock Pipe
Type : Circular Mild Steel
Length : 450 m
Diameter : 3.1m
Powerhouse
Type : Surface
Dimension : L = 40 m, W = 18 m H = 15 m
Tailrace
Type : Rectangular box
Length : 30 m
Dimension : W = 6 m, H = 4 m
Turbines
Type of Turbine : Vertical Francis
Number : Two (2)
Net head : 204.61 m
Rated Output : 40 MW
Unit Discharge : 11.4 m3/s
Transmission & Interconnection
Power House – Balanch Substation : 16 km
Voltage : 132 kV
Interconnection Point : 132 kV NEA Balanch Substation

Current Status

 

The company had obtained the Survey Licence of the Project for 40 MW on dated 18th Falgun, 2072 from Department of Electricity Development, Ministry of Energy and completed the detailed Survey of the Project which is carried out by our Consultant South Asia Engineering Pvt. Ltd. The Company has entered a Power Purchase Agreement PPA for the Project with Nepal Electricity Authority on dated 15th Falgun, 2075 B.S. Company has also obtained the Generation License  from Ministry of Energy, Department of Electricity Development on dated 12th Ashwin, 2076 B.S. Syndicated Credit Facilities Agreement has been signed for the Project with Consortium Banks (Himalayan Bank Limited as Lead with Employees Provident Fund, Nepal Bank Limited, Rastriya Banijya Bank Limited, Nepal Bangladesh Bank Limited and Century Commercial Bank Limited as Members) and Api Power Company Limited on dated 27th September, 2020.

 

The project construction work has been started since 1st Kartik, 2077 B.S. 

Market Price

Today's Nepal Share Market


Max Price Min Price Closing Price Prev. Closing Diff.
340 307 315 326 -11

 


Latest News

Location

Navigation

  • Home
  • Organizational Structure
  • Board Of Directors
  • Projects
  • Gallery
  • Career
  • Contact Us

Our associates

 
  • Trade Tower Business Center
  • Arun Valley Hydropower Development
  • Rairang Hydropower Development
  • Siddhakali Power Limited
  • Ridi Hydropower Company Limited
  • Makalu Developers Limited
  • SAE
  • Janataresidency
  • Peoples Investment Company
  • Arun Kabeli Power Ltd
  • Ingwa Hydro Company
  • Palanchowk
  • Api Hydro Mechanical Limited

Contact Us

Email Address:- info@apipowercom.np

Address:- 4th Floor, Trade Tower Nepal, Thapathali, Kathmandu

Telephone:- +977-1-5111037/93/56

Copyright © 2016 Api Power Company Limited. Powered By  Nepdroid Innovations